M/s. Esor Construction Pty Limited, South Africa have constructed the water supply pipeline for Swaziland Water and Sewerage Corporation as a part of the African Development Bank financed "Ezulwini Sustainable Water Supply Project" for increasing the supply network to the Ezulwini area.
Swaziland Water Services Corporation (SWSC)
African Development Bank (AfDB)
Aurecon Group, Swaziland
ESOR Construction Pty Limited, South Africa
M/s. Electrotherm India Limited supplied the 2.9 km long DN 500mm C30 Ductile Iron Pipes to EN 545: 2010 in May 2019 and the pipeline was installed and commissioned in September 2019.
Total tonnage: 277 MT
The pipeline has been installed, tested, commissioned and is now fully operational.