Ntungamo Water Supply Project, Uganda
- Client: Ministry of Water & Environment, Government of Uganda
- Consultant: M&E Associates, Uganda
- Contractor: Vidas Engineering Services Limited, Uganda
- Products: DI flanged pipes, fittings, couplings, adaptors & valves
- Tonnage – 18.5 tons
- Completed in 2015
Keroka - Isebania Water Supply Project
- Client: Lake Victoria South Water Services Board (LVSWSB)
- Project Name: Construction of Short Term Water Supply Works-LVWATSAN II STI
- Financed by: African Development Bank (AFDB)
- Consultants: Gibb Africa Limited
- Contractor: Zhongmei Engineering Group (Kenya) Limited
- Products: DI valves, couplings, flange adaptors and specials
- Completed in 2015
Construction of Lirima Gravity Flow Scheme Water Supply & Sanitation Project - Phase II
- Client: Ministry of Water & Environment, Government of Uganda
- Consultant: SGI - Studio Galli Ingegneria S.r.l.
- Contractor: Beijing Uni Construction Co. Limited, Uganda
- Products: Gate Valves, Air Valves, Float Valves & Bulk Water Meters DN 50-250mm PN16 / PN25 - 3.5 tons (111 pcs.)
- DI Flanged Pipes, Fittings, Couplings and Adaptors – 17.0 tons
- Completed in August 2019
Hydraulic Improvement Works at Agoro Irrigation Scheme in Lamwo District
- Client: Ministry of Water & Environment (MWE), Govt. of Uganda
- Financed by: African Development Bank (AFDB)
- Contractor: Gets Technical Services Limited, Uganda
- Products: Double Gate Valves DN 200-700mm PN10 and Surface Boxes - Tonnage – 31.0 tons (238 pcs.)
- Completed in Jan 2020
Construction of New Govt. City at Ihumwa - Dodoma Municipality
- Client: Dodoma Urban Water Supply & Sanitation Authority (DUWASA)
- Contractor: Oriental Construction Co. Limited, Kenya
- Products: Gate Valves, Air Valves, Float Valves & Bulk Water Meters DN 50-350mm PN16 / PN25
- Tonnage – 3.0 tons
- Completed in 2018
Extension of Water Transmission Pipeline from Lake Victoria Water Supply Scheme to Kagongwa & Issaka Towns – Lot 1
- Client: Ministry of Water & Irrigation, Govt. of Tanzania / Kahama – Shinyanga Water Supply & Sanitation Authority Tanzania
- Financed by: African Development Bank (AFDB)
- Contractor: Oriental Construction Co. Limited, Kenya
- Products: Gate Valves, Air Valves, Butterfly Valves & Meters, DN 50-350mm PN40 - Tonnage – 10.0 tons
- Completed in May 2019
Construction & Completion of Orkesumet Water Supply Project – Lot II
- Client: Ministry of Water & Irrigation, Tanzania
- Consultant: Shoura Consult Co. Ltd., Sudan
- Financed by: BADEA + OFID
- Contractor: Jandu Plumbers Ltd., Tanzania
- Products: Gate Valves, Butterfly Valves, Check Valves, Air Valves, Bulk Water Meters, Electromagnetic Flow Meters PN16-PN40
- Volume: Valves and Meters – 505 pieces (46.5 tons)
- Year supplied: Supplies completed in Jan. 2020 – installed and project commissioned in May 2021
Lot 2 – Construction of Chogoriya Water Supply Infrastructure
- Client: Tana Water Works Development Authority, Kenya
- Consultant: Mangat, I.B. Patel Limited (MIBP), Kenya
- Financed by: African Development Bank (AfDB)
- Contractor: Oriental Construction Co. Limited, Kenya
- Products: Valves, Penstocks and Water Meters – DN 50mm to 450mm PN16
- Volume: Tonnage – 17 tons (331 pcs.)
- Year supplied: Completed in May 2020
Construction Works for Kiptogot-Kolongolo Water Supply Project
- Client: Rift Valley Water Works Development Authority, Kenya
- Consultant: Studio Galli Ingegneria with SARI Consulting
- Financed by: African Development Bank (AfDB)
- Contractor: Zhongmei Engineering Group Limited, Kenya
- Products: Valves, Penstocks and Water Meters – DN 50mm to 500mm PN16/25
- Volume: Tonnage – 48 tons (508 pcs.)
- Year supplied: Completed in May 2021